Project Status

Sydney Ports received planning approval from the Department of Planning to develop a second Bulk Liquids Berth (BLB2) at Port Botany in March 2008.

WorleyParsons Services was selected as the design consultant for the project in May 2009 and the BLB2 final design was completed in March 2010.

Tenders for the construction of the Bulk Liquids Berth 2 were requested from four shortlisted companies in December 2010 and closed in February 2011.

Following an extensive evaluation process, the Board of Sydney Ports Corporation approved the award of the construction contract to John Holland.

Construction has commenced and the berth is expected to be operational for trade in mid 2013.