Milestones achieved as at the end of September 2009 include:
- Sydney Ports is progressing final authority approvals following completion of the 100% design documentation for the ILC base infrastructure and off site works.
- On this basis, the project’s design consultant Maunsell Aecom is preparing tender documents for the main construction contract.
- The Wheel Lathe rail corridor works were completed on 25 August 2009.
- The demolition of all existing site infrastructure is nearing completion. The south sidings rail lines will soon be removed now that the north sidings rail corridor has been constructed and commissioned to provide access to the wheel lathe facility.
- The second meeting of the Community Liaison Committee was held on site on 26 August 2009.
To read the full September 2009 ILC at Enfield Project Update please click here